 Brown County 2015 Construction Outlook


Mainline US 41
March 2012 through December 2016
  • Mainline segments under construction in 2015: Glory Road to 9th Street; Memorial Drive to Lakeview Drive.
  • Reconstruction of US 41 mainline and structures.
  • Two lanes of traffic in each direction with reduced shoulders and lane widths.
  • Expect periodic nighttime lane restrictions and/or ramp closures.
 
I-43 Interchange
September 2013 through December 2016
  • Reconstruction and improvement of the system-to-system interchange.
  • The following ramps will CLOSE in 2015:
    • northbound US 41 to southbound I-43 for seven months between March – September 2015
    • southbound US 41 to southbound I-43 and northbound I-43 to southbound US 41 for 12 months between October 2015 – September 2016
    • Intermittent nighttime lane and ramp closures will occur throughout 2015
 
Velp Avenue Interchange
February 2015 through June 2017
(Preliminary work began in 2013)
  • Reconstruction of the Velp Avenue interchange.
  • Expect intermittent nighttime lane and ramp closures throught 2015 
    • The southbound US 41 exit ramp to Velp Avenue will CLOSE for 13 months between October 2015 – October 2016
    • The Velp Avenue to northbound US 41 ramp will CLOSE for five months between July – November 2015
 
Morris Avenue
March 2014 through 2015
  • Reconstruction of the US 41 bridges over Morris Avenue.
  • Morris Avenue will have lane restrictions and intermittent nighttime closures.
  • Morris Avenue may CLOSE for 30 days–outside the school year–to help expedite the work. The 30-day closure would not be concurrent with a Cormier Road closure.
    • Cormier Road and Lombardi Avenue will serve as alternate routes when Morris Avenue is closed.
 
Cormier Road
March 2014 through 2015
  • Reconstruction of the US 41 bridges over Cormier Road.
  • Cormier Road will have lane restrictions and intermittent nighttime closures.
  • Cormier Road may CLOSE for 30 days–outside the school year–to help expedite the work. The 30-day closure would not be concurrent with a Morris Avenue closure.
    • Morris and Lombardi Avenues will serve as alternate routes when Cormier Road is close
WIS 172 Ramps
Fall 2013 through summer 2016
  • Reconstruction of WIS 172 ramps and mainline at US 41. 
  • The eastbound WIS 172 to southbound US 41 ramp will CLOSE for reconstruction in late 2015 or early 2016; the southbound US 41 to westbound WIS 172 ramp will CLOSE for 14 days in fall of 2015.
  • Intermittent nighttime lane and ramp closures will occur throughout 2015.
Waube Lane/Oneida Street Interchange
September 2013 through summer 2016
  • Reconstruction of the US 41 bridges over Waube Lane/Oneida Street.
  • Interchange and Waube Lane/Oneida Street will remain open during construction with intermittent nighttime lane and ramp closures. Left turn lanes on Waube/Oneida at the interchange will be maintained, and westbound traffic will be reduced to one lane with turn lanes for a stage of the project.

Parkview Road
August 2013 through 2015
  • Reconstruction of the US 41 bridges over Parkview Road.
  • Lane restrictions may occur.