 Brown County 2014 Construction Outlook 


Mainline US 41
Mainline segments under construction in 2014: Glory to 9th; Larsen to Memorial; Duck Creek to Lineville
March 2012 through December 2016
  • Reconstruction US 41 mainline and structures.
  • Two lanes of traffic in each direction with reduced shoulders and lane widths.
  • Expect periodic nighttime lane restrictions and/or ramp closures.


Lineville Road Interchange

June 2013 through May 2015

  • Reconstruction of the Lineville Road interchange.
  • Reduced Lane widths on Lineville from January through August 2014.
  • The interchange will CLOSE for 60 days between August - October 2014.


I-43 Interchange

September 2013 through December 2016

  • Reconstruction and improvement of the system-to-system interchange.
  • The following ramps will CLOSE for 30 days in spring/summer of 2014 while girders are erected:
    • Northbound US 41 to southbound I-43
    • Northbound I-43 to southbound US 41
    • Northbound US 41 on-ramp from Velp Avenue
    • Southbound US 41 off-ramp to Velp Avenue
  • Intermittent nighttime lane restrictions.
  • Ramp closures and/or freeway closures may occur throughout 2014.


Velp Avenue Interchange

February 2015 through June 2017

  • Reconstruction of the Velp Avenue interchange.
  • Beginning in 2014, expect intermittent nighttime lane and ramp closures.
    • Eastbound Velp Avenue will be restricted to one lane for 21 consecutive days in spring 2014.
    • Southbound off-ramp to Velp Avenue will CLOSE for 30 days in spring of 2014 as part of the I-43 interchange work.


WIS 29 System Interchange

September 2012 through November 2014

  • Reconstruction as a system-to-system interchange and service interchange.
  • The Shawano Avenue Interchange will CLOSE for 60 days between June – September 2014.
  • The Packerland Drive/Cardinal Lane interchange will CLOSE for 60 days between August – November 2014.
  • Elmhurst Drive and Cardinal Avenue roundabout construction will result in reduced lanes and nighttime closures on Cardinal Avenue between July – November 2014.
  • Larsen Road will CLOSE under US 41 for 15 consecutive days in the Spring of 2014 for reconstruction.

 
Morris Avenue

March 2014 through 2015

  • Reconstruction of the US 41 bridges over Morris Avenue.
  • Lane restrictions and intermittent nighttime closures in 2014.
  • Morris Avenue may CLOSE for 30 days outside the school year. This closure will not be concurrent with the Cormier Road 30-day closure.


Cormier Road

March 2014 through 2015

  • Reconstruction of the US 41 bridges over Cormier Road.
  • Lane restrictions and intermittent nighttime closures in 2014.
  • Cormier Road may CLOSE for 30 days outside the school year. This closure will not be concurrent with the Morris Avenue 30-day closure.


WIS 172 Ramps

Fall 2013 through Summer 2016

  • Reconstruction of WIS 172 ramps and mainline at US 41.
  • Eastbound WIS 172 ramp to northbound US 41 will remain CLOSED through summer 2014.
  • The northbound US 41 to westbound WIS 172 ramp will have 14 day CLOSURE.

ALTERNATE ROUTE: Eastbound WIS 172 to northbound US 41 and northbound US 41 to westbound WIS 172 ramp closures – Continue east on WIS 172, exit on Vanderperren Way, then Vanderperren Way to Holmgren Way to Pilgrim Way to westbound WIS 172.


Hansen Road Bridge

September 2013 through Summer 2014

  • Reconstruction of Hansen Road Bridge over US 41.
  • Bridge is CLOSED through summer 2014.

ALTERNATE ROUTE: South Ridge Road to Waube Lane/Oneida Street


Waube Lane/Oneida Street Interchange

September 2013 through Summer 2016

  • Reconstruction of the US 41 bridges over Waube Lane/Oneida Street.
  • Interchange and Oneida Street will remain open during construction with intermittent nighttime lane and ramp closures.


Parkview Road

August 2013 through Summer 2016

  • Reconstruction of the US 41 bridges over Parkview Road.
  • Reduced lane and shoulder widths.
  • Parkview Road will CLOSE for 45 days in fall 2014.

For more information about projects and traffic impacts, visit the Brown County Project Briefs page


Winnebago County 2014 construction outlook

Although major construction activities are complete in Winnebago County, two overpasses—County GG and County Y—will be CLOSED between March - August. Lane closures on US 41 may occur.


For more information about projects and traffic impacts, visit the Winnebago County Project Briefs page.



Schedules are subject to change. Please visit the Closures page for regularly updated closure information and project progress.