Brown County 2013 Construction 


Lineville Road Interchange
June 2013 through May 2015
  • Reconstruction of Lineville Road interchange.
  • Interchange will remain open in 2013 with intermittent lane and ramp closures.
  • The Lineville Road interchange will CLOSE for 60 days between August - October 2014.

I-43 Interchange and Velp Avenue

September 2013 through December 2016
  • Early structure work in advance of the reconstruction of the I-43 interchange.
  • The Beaver Dam Creek box culvert is also being reconstructed under US 41 just south of Velp Avenue (March 2013 through July 2014).
  • Intermittent ramp closures and lane restrictions will occur in 2013.

Leo Frigo Memorial Bridge and I-43

April 2012 through July 2013
  • Improving and resurfacing deteriorating pavement on the bridge and portions of I-43, including repairs to bridges and local intersections.
  • Traffic will be restricted to one lane in each direction on I-43 from April through July 2013 which could cause significant travel delays.
  • Ramp CLOSURES will occur at the Atkinson Drive and Webster Avenue interchanges from April through July 2013.
  • Military Avenue overpass will CLOSE for 40 days between May - June 2013.

WIS 29 System Interchange

September 2012 through October 2014
  • Reconstruction as a system-to-system interchange and service interchange.
  • Westbound traffic routed onto newly-aligned Shawano Avenue and WIS 29 on-ramp at Packerland Drive.
  • Eastbound traffic routed onto the WIS 29 off-ramp, north along Packerland Drive and east along newly-aligned Shawano Avenue (WIS 29).
  • Intermittent ramp closures and lane restrictions will occur in 2013.
  • Southbound US 41 exit to Mason Street will be accessed by a temporary ramp from Shawano Avenue in 2013.

9th Street

June 2013 through August 2013
  • Reconstruction of 9th Street roadway and sidewalks under US 41.
  • 9th Street at US 41 will CLOSE for 40 days between June - August 2013.

Morris Avenue

August 2013 through 2015
  • Preparation for major construction planned for Fall 2014.
  • Intermittent lane closures and restrictions along Morris Avenue in 2013.
  • Morris Avenue will CLOSE for 30 days between June - August 2014, and again for 30 days between June - August 2015.
  • The roadway will remain open during Packer games and Morris Avenue will not be closed simultaneously with Cormier Road.

Cormier Road

August 2013 through 2015
  • Preparation for major construction planned for Fall 2014.
  • Intermittent lane closures and restrictions along Cormier Road in 2013.
  • Cormier Road will CLOSE for 30 days between June - August 2014, and again for 30 days between June - August 2015.
  • The roadway will remain open during Packer games and it will not be closed simultaneously with Morris Avenue.

WIS 172 Ramps

Fall 2013 through Summer 2015
  • Reconstruction of WIS 172 ramps and mainline at US 41.
  • Eastbound WIS 172 to northbound US 41 ramp will CLOSE starting in Fall 2013.
  • Intermittent ramp and lane closures on westbound WIS 172 to southbound US 41 and eastbound and westbound WIS 172 mainlines at US 41 will occur starting in Fall 2013.
  • The northbound US 41 to westbound WIS 172 ramp will CLOSE for 14 days in Summer 2014
  • The southbound US 41 to westbound WIS 172 ramp will CLOSE for 14 days in Fall 2015.
ALTERNATE ROUTE: Packerland Drive to Lombardi Avenue


Hansen Road Bridge

September 2013 through August 2014
  • Reconstruction of Hansen Road bridge over US 41.
  • Bridge will CLOSE between September 2013 - August 2014.
ALTERNATE ROUTE: South Ridge Road to Waube Lane/Oneida Street


Waube Lane/Oneida Street Interchange

September 2013 through Fall 2015
  • Preparation in 2013 and 2014 for major construction in 2015.
  • Interchange and Oneida Street will remain open during construction with intermittent nighttime lane and ramp closures.

Parkview Road

August 2013 through 2015
  • Preparation in 2013 for major construction planned for 2014.
  • Intermittent lane closures and restrictions will occur along Parkview Road.
  • Parkview Road will CLOSE for 45 days in Summer/Fall 2014.

Grant Street
May through June of 2013
  • Grant Street will be reconstructed under US 41. The purpose is to lower Grant Street to allow for sufficient clearance under US 41 and to improve sight distance on Grant Street.
  • Grant Street, including the intersection of Mid Valley Drive will be CLOSED for approximately 40 days between May - June 2013.
ALTERNATE ROUTE: Main Avenue and Scheuring Road


US 41 
Mainline 
Mainline segments under construction in 2013: Orange to 9th; Larsen to Memorial; Duck Creek to Lineville March 2012 through July 2016
  • Reconstruction of US 41 mainline and structures.
  • The US 41 mainline will have two lanes of traffic in each direction, with nighttime lane restrictions and/or ramp closures.
For more information about projects and traffic impacts, visit the Brown County Project Briefs page


Winnebago County 2013 construction outlook


US 41 Mainline
Witzel Avenue to US 41 August 2011 through July 2013, US 45 to Breezewood Lane April 2011 through May 2013
  • Reconstruction of northbound US 41 lanes.
  • Mainline US 41 will have two lanes of traffic in each direction.
  • Expect periodic nighttime lane closures from 7 p.m. to 5 a.m. 

Lake Butte des Morts Causeway
September 2011 through July 2013
  • Construction continues on the new northbound lanes and the new northbound structure over the Lake Butte des Morts main channel.
  • Two lanes of traffic will remain open in both directions, but lanes and shoulders will be narrow; motorists may experience temporary nighttime closures as trucks and equipment move in and out of the work zone.

WIS 44 Interchange

April 2013 through November 2013
  • Replace the southeast wing on the WIS 44 structure over US 41.
  • Replace concrete pavement approaches to the WIS 44 structure.
  • Install paver bricks and landscaping in the WIS 44 median.
  • No impact to US 41 traffic, but lane closures on WIS 44 will occur daily when work is being completed in the area.
  • WIS 44 will be down to one lane in each direction on the WIS 44 structure for eight weeks while work is completed on this structure and pavement approaches.
For more information about projects and traffic impacts, visit the Winnebago County Project Briefs page.

Schedules are subject to change. Please visit the Closures page for regularly updated closure information and project progress.